Quick answer
Three-point estimating: Optimistic, Most likely, Pessimistic → expected = (O+4M+P)/6 (PERT) or (O+M+P)/3 (triangular) — the honest estimate that carries its uncertainty.
The three numbers
O (best case), M (most likely), P (worst case) — the range captures the uncertainty a single number hides.
Join Doitify Today
Move projects forward without the chaos: all your tasks, progress, and team reports in one unified workspace. Built for companies, startups, and remote teams — with a quick setup and a free trial.
The formulas
Triangular: (O+M+P)/3; PERT beta: (O+4M+P)/6 — PERT weights the likely; use PERT for skewed guesses.
The variance
(P-O)/6 = standard deviation — the spread tells you how uncertain the estimate is.
Using them
Three points on uncertain tasks → expected values + confidence ranges on the schedule.
Bottom line
Three-point estimating: Optimistic, Most likely, Pessimistic → expected = (O+4M+P)/6 (PERT) or (O+M+P)/3 (triangular) — the honest estimate that carries its uncertainty.
FAQ
If this post was helpful, you might also enjoy Resource Scheduling: Complete Guide and Project Management Software for Research Teams: 2026 Guide.
Join Doitify Today
Move projects forward without the chaos: all your tasks, progress, and team reports in one unified workspace. Built for companies, startups, and remote teams — with a quick setup and a free trial.