Quick answer
Estimating project duration: sum the critical path (with buffers), not all tasks — parallel work doesn’t add; the longest chain sets the length.
The math
The critical path’s sum = project duration — parallel paths don’t add, they overlap.
Join Doitify Today
Move projects forward without the chaos: all your tasks, progress, and team reports in one unified workspace. Built for companies, startups, and remote teams — with a quick setup and a free trial.
Three-point durations
Expected = (O+4M+P)/6 per critical task — the range gives the range of finishes.
Adding buffer
Project buffer on the chain (critical chain style) — the schedule’s honest margin.
The sanity check
Comparable history — ‘how long did similar take?’ is the reality check the math needs.
Bottom line
Estimating project duration: sum the critical path (with buffers), not all tasks — parallel work doesn’t add; the longest chain sets the length.
FAQ
If this post was helpful, you might also enjoy What Is Definition of Done in Scrum? A Complete Guide with Examples and How to Keep a Project on Track: Early-Warning Tips.
Join Doitify Today
Move projects forward without the chaos: all your tasks, progress, and team reports in one unified workspace. Built for companies, startups, and remote teams — with a quick setup and a free trial.