Quick answer
CPM uses single-point durations on the critical path (deterministic); PERT uses three-point estimates (probabilistic) — CPM for known work, PERT for uncertain work.
CPM
Deterministic durations → one critical path, one finish date — for well-understood work.
Join Doitify Today
Move projects forward without the chaos: all your tasks, progress, and team reports in one unified workspace. Built for companies, startups, and remote teams — with a quick setup and a free trial.
PERT
Three-point durations → expected dates + variance — for uncertain, research-type work.
The calculation
CPM: sum the path. PERT: (O+4M+P)/6 per task, then the path — plus variance math.
Choosing
Known construction-style work → CPM; R&D uncertainty → PERT; modern tools blend both.
Bottom line
CPM uses single-point durations on the critical path (deterministic); PERT uses three-point estimates (probabilistic) — CPM for known work, PERT for uncertain work.
FAQ
If this post was helpful, you might also enjoy Project Manager vs Product Owner: What’s the Difference? and Project Timeline: How to Create One (Step-by-Step Guide).
Join Doitify Today
Move projects forward without the chaos: all your tasks, progress, and team reports in one unified workspace. Built for companies, startups, and remote teams — with a quick setup and a free trial.