Why do teams leave Runn in the first place?
Five reasons come up repeatedly, and only one of them is about price.
Planning without delivery. Runn answers “who is busy in March”. It does not answer “is this project going to land”, because task-level delivery, dependencies and acceptance criteria live elsewhere. Teams end up running two tools and reconciling them weekly.
Client and stakeholder visibility. Resource plans are internal by design. The moment a client asks for a status view, someone builds a slide.
Pricing at scale. Runn prices per planned person, which is fair for the value delivered but grows linearly with headcount. A 40-person consultancy paying per planner starts comparing against tools that bundle planning into a broader suite at a similar per-seat rate.
Reporting depth. Utilisation and forecast reports are good; project profitability, per-client margin and pipeline-weighted forecasts are thinner than PSA suites offer.
Integrations and setup. Getting time entries from a delivery tool into a forecasting tool requires either double entry or an integration that somebody has to maintain.
Notice that four of the five are “we need something adjacent”, not “this is bad”. That distinction matters when you evaluate replacements: the alternative only wins if it covers the adjacent need without losing the forecasting you already rely on.
What are the best Runn alternatives in 2026?
Eight options, grouped by what they actually replace.
| Tool | Best for | List price, 2026, per user/month, annual | Free plan | Main trade-off |
|---|---|---|---|---|
| Runn (baseline) | Revenue and utilisation forecasting | Roughly $8–$14 per planned person | Trial only | Planning-only; two-tool workflow |
| Float | Day-level scheduling | From about $7 (Basic) to about $13 (Pro) | No | Scheduling only; weak project delivery |
| Resource Guru | Cheap scheduling plus leave | Free up to 10 resources; about $4.50 (Blue), $8 (Blackbelt) | Yes, 10 resources | Limited project and financial depth |
| Teamdeck | Resource planning plus time tracking | From about $4 to about $9 | Trial only | Smaller ecosystem; lighter reporting |
| Forecast | PSA with AI-assisted planning | Custom quote; commonly around $25–$30 | No | Price; heavier implementation |
| ClickUp | Planning inside a delivery suite | $7 (Unlimited), $12 (Business) | Yes, generous | Resource view is bolt-on, not core |
| Wrike | Enterprise delivery with resource add-ons | About $10 (Team), $25 (Business) | Yes, limited | Resource planning costs extra |
| monday.com | Visual delivery plus workload | $9 (Basic), $12 (Standard), $19 (Pro), 3-seat minimum | Yes, 2 seats | Workload view needs Standard or above |
Prices are list prices before tax and before annual discounts vary by region. Verify before you model a budget; every vendor in this table has repriced at least once since 2023, and the tiers move more often than the features do.
Join Doitify Today
Move projects forward without the chaos: all your tasks, progress, and team reports in one unified workspace. Built for companies, startups, and remote teams — with a quick setup and a free trial.
How does Float compare with Runn?
Float is the closest functional swap. It schedules people by the day, handles tentative bookings, shows utilisation per person, and has a clean interface that a non-technical studio manager can learn in an afternoon.
Where it beats Runn: simplicity and price. A 22-person team on Float’s basic tier pays roughly $1,850 a year against Runn’s $2,600–$3,700, and the scheduling screen needs less configuration.
Where it loses: Float is scheduling, not forecasting. It will show you that a designer is 120% booked in week 14; it will not model what that does to revenue, margin or the pipeline. If your monthly board pack includes a revenue forecast built from planned hours, Float does not replace it.
Float is the right answer for agencies whose planning question is “who is free next week” and whose financial reporting already happens in a spreadsheet or an accounting system.
How does Resource Guru compare with Runn?
Resource Guru is the value option. A genuinely usable free plan for up to ten resources, then a low per-person price, plus leave management that is better than most competitors at any price.
It handles the two questions a small studio asks most often: who is available, and who is on holiday. Booking, availability, and a simple utilisation report cover about 80% of what a 15-person agency needs.
Where it loses: depth. Project-level budgeting, revenue forecasting and client profitability are not its job. For a team of 30 with a finance function asking for margin by client, Resource Guru becomes one of three tools rather than a replacement.
It is, however, the cheapest credible answer in this list, and the free tier makes it the obvious first test for a team of ten or fewer.
How does Teamdeck compare with Runn?
Teamdeck combines resource planning with time tracking, which sounds like a small addition and is not. When planned hours and actual hours live in the same system, utilisation stops being an estimate.
That matters for billing. A team that plans 120 hours and logs 148 on a fixed-fee project has found a margin problem in week two rather than at invoice time. Teamdeck’s pricing, from roughly $4 to $9 per person per month, makes that visibility cheap.
Where it loses: ecosystem and reporting polish. Fewer integrations, lighter financial modelling, and less depth in forecasting than Runn. It also expects the team to log time consistently, which is a cultural change as much as a software one.
How does Forecast compare with Runn?
Forecast is the upgrade path for teams that have outgrown planning-only. It combines resource planning with project management, time tracking, budgeting and margin reporting, and its AI features estimate task duration and utilisation from historical data.
Where it wins: one system from plan to invoice, with profitability per project rather than per person. For a 50-person consultancy billing $6m a year, a two-point margin improvement is $120,000, which dwarfs any licence difference in this table.
Where it loses: price and weight. Expect roughly $25–$30 per user per month, plus an implementation that takes weeks, plus a workflow your team must actually adopt. For a 12-person studio, it is a sledgehammer.
How do ClickUp, Wrike and monday.com fit in?
These are delivery suites that added resource views. They make sense when the real problem is tool sprawl rather than planning depth.
ClickUp at $7–$12 per user per month includes workload views, dashboards, docs, goals and time tracking. The resource view is real but simpler than Runn’s: it shows allocation per person, not revenue impact. Its advantage is that planning and delivery share one task database.
Wrike at roughly $10–$25 includes resource management on higher tiers, with strong proofing and approvals for agency work. Its enterprise reporting is the best of the three, and its pricing reflects that.
monday.com at $9–$19 with a three-seat minimum has the gentlest adoption curve and a workload view on Standard and above. It is weakest on financial forecasting of the three.
The trade-off is consistent across all three: you gain one place for work and lose the depth of a dedicated planning engine. Teams that forecast revenue weekly will feel that loss; teams that schedule and then execute will not.
What does each option cost at 15, 30 and 60 people?
Three worked examples, annual list price, counting only the seats you would actually buy.
15 people, all planned. Runn at $10: 15 × $10 × 12 = $1,800. Float Basic at $7: $1,260. Resource Guru Blue at $4.50: $810. Teamdeck at $6: $1,080. ClickUp Business at $12: $2,160. Forecast at $27: $4,860.
30 people, 22 planned. This is where per-planned-person pricing starts to show its logic. Runn charges for 22: 22 × $10 × 12 = $2,640. Float charges for users with access, roughly 26 including managers: 26 × $7 × 12 = $2,184. Resource Guru for 30 resources on Blue: $1,620. ClickUp for 30 seats on Unlimited: $2,520. Forecast for 30: $9,720.
60 people, 45 planned, two offices. Runn for 45: $5,400. Float for 55 users on Pro at $13: $8,580. Resource Guru Blackbelt at $8 for 60: $5,760. Wrike Business at $25 for 60: $18,000. Forecast for 60: $19,440.
Two patterns emerge. First, the spread within the “scheduling only” group is small in absolute terms — a few thousand dollars a year at most — so feature fit should decide, not price. Second, once you cross into PSA or enterprise delivery suites, the licence becomes a five-figure line and the justification has to come from margin or headcount avoided, not from convenience.
How do you calculate whether the switch pays for itself?
Use utilisation, because that is the number these tools exist to move.
Example 1, the utilisation gain. A consultancy with 18 billable consultants has 18 × 1,720 available hours a year, or 30,960 hours. At 68% utilisation, billable hours are 21,053. At 73%, they are 22,601 — a gain of 1,548 hours. At a $115 blended rate, that is $178,020 of additional revenue, or roughly $106,800 of gross margin at 60% delivery cost. Against a $2,640 annual licence, the question stops being about price.
The catch: a tool does not create 1,548 hours. It makes the gaps visible. The realistic claim is that better visibility recovers one to three points of utilisation, not five, and only if someone acts on the report weekly.
Example 2, the double-entry cost. A team running Runn plus a delivery tool spends about 3 hours a week reconciling: exporting time entries, checking bookings against tasks, fixing mismatches. That is 156 hours a year. At a $55 loaded rate, $8,580 — more than the licence of either tool. This is the strongest argument for consolidation, and the weakest argument for switching to a tool that fits worse.
Example 3, the migration cost. Moving 22 people with four years of time entries (roughly 12,000 rows) takes about 3 days of data work, plus two weeks of parallel running at 2 hours per person: 44 hours. Total, around 68 hours, or $3,740 at $55. Any switch should be justified over 18 months, not 6.
When should you stay on Runn?
Stay when the weekly question is genuinely “what does the next quarter look like in revenue”, and when the answer currently comes from Runn’s forecast rather than a spreadsheet. Replacing a forecasting engine with a scheduler is a downgrade dressed as a saving.
Stay also when the team has finally adopted the workflow. The cost of a migration is not the licence delta; it is the six weeks of reduced adoption that follows, during which nobody trusts the numbers in either system.
And stay if the adjacent needs are solvable more cheaply than by switching: a client status view can come from a shared report, and project delivery can come from a lightweight task tool wired to the same people list. Two focused tools that are actually used beat one suite that is half configured.
What are the hidden costs of switching?
Four, and the first is the one people forget.
The re-learning curve. A resource planner is used by studio managers and finance. A delivery suite is used by everyone. Rolling a new tool to 60 people costs roughly half a day each: 30 hours, plus a two-week throughput dip.
Data loss in the seams. Historical bookings and time entries rarely migrate cleanly. Expect to keep the old tool read-only for a quarter, which means paying for both.
Reporting rebuild. Every custom report in Runn has to be rebuilt, and the first version will be wrong. Budget a day per report.
Integration drift. If you consolidated two tools into one, the integration disappears, which is a saving. If you split one tool into two, you have added one, which is a cost.
Which alternative fits which team?
Six profiles, one recommendation each.
- 12-person design studio, no finance function: Resource Guru, free tier first, Blue when you pass ten people.
- 22-person agency, weekly scheduling, monthly revenue forecast: stay on Runn, or move to Forecast if margin reporting is the real gap.
- 30-person consultancy that bills hourly and suspects leakage: Teamdeck, because planned versus actual is the whole game.
- 40-person product company with no billable hours: ClickUp or monday.com; resource planning matters less than delivery visibility.
- 60-person firm with two offices and an enterprise client: Wrike Business, for approvals and reporting depth.
- Team that bought Runn and never used the forecast: Float Basic, and put the savings into a delivery tool.
How does Doitify fit into this comparison?
Doitify is our product, so treat this section as disclosure rather than an independent verdict. It is a project management workspace: tasks, sub-tasks, checklists, owners and due dates, with Kanban, Gantt with dependencies, roadmap, calendar, workload and utilisation views, plus work and performance reports. Time tracking and reporting sit in the same data model as the tasks.
Where that fits the Runn question: teams that wanted one place for the plan, the work and the report, and found that a dedicated forecasting engine plus a separate delivery tool meant paying twice and reconciling weekly. Doitify Copilot can draft a plan from a stated goal, which shortens the setup that usually stalls a migration.
Where it does not fit: a consultancy that needs revenue forecasting weighted by pipeline and margin by client. That is a PSA problem, and Forecast or a finance system is the right answer. Doitify also will not match Runn’s depth in scenario modelling across a 12-month horizon.
The honest test is a two-week parallel run on one real project, measured on the question you actually ask every Monday.
FAQ
Conclusion
The best Runn alternative is not the one with the most similar feature grid. It is the one that answers the question your team asks every Monday, at a price that survives a headcount review.
If that question is about revenue and utilisation, stay on Runn or move up to Forecast. If it is about who is free next week, Float or Resource Guru will do it for less. If it is about running the work at all, the delivery suites win and you accept a weaker planning view. Whichever way you go, budget for the migration honestly: the licence is the cheap part.