Why do generic project tools fail on a mine site?
They fail on three specifics, and none of them is about features in the ordinary sense.
The first is connectivity. A pit, a decline, a concentrator, and a tailings facility are not offices. Coverage is patchy, satellite links add latency, and a tool that requires a live connection to update a task does not get updated. Offline capture with conflict-aware sync is a hard requirement, not a nice-to-have.
The second is safety obligations. Work on site is governed by permits, isolations, and hazard assessments, and those are legal artefacts. A project tool that treats “permit approved” as a status dropdown, with no record of who approved what and when, creates exactly the evidence gap an investigation will look for.
The third is the cost of a single day. In an office, a slipped task costs a meeting. On a mine, a slipped shutdown day costs production, and production is measured in thousands of tonnes. Software decisions that ignore this asymmetry optimise the wrong thing: they save 20,000 dollars on licences and add a week to a turnaround.
There is a fourth, quieter issue: terminology. Mining projects are structured by work breakdown into disciplines, areas, and packages, with cost codes that must reconcile to finance. A tool built around boards and cards forces teams to encode that structure in naming conventions, which is where reporting accuracy goes to die.
What should mining companies actually require?
Nine requirements separate a workable system from a demo that impresses the wrong people.
| Requirement | Why it matters on a mine | What to test |
|---|---|---|
| Offline capture and sync | Pit and underground coverage is unreliable | Create and edit tasks offline, then sync with conflicts |
| Permit and isolation workflows | Legally significant approvals, not status labels | Approval chain, timestamps, immutable history |
| Contractor onboarding | Rotating workforce, induction and competency checks | Gate task assignment on induction status |
| CMMS integration | Equipment status must agree across systems | Two-way sync with SAP PM, Maximo, or Hexagon |
| Cost and progress reconciliation | Earned value against the project budget | WBS roll-up to cost codes and commitments |
| Schedule rigour | Critical path across thousands of activities | Import and export P6 XER or XML |
| Document control | Drawings, revisions, and transmittals | Revision control and controlled distribution |
| Audit trail and retention | Regulator and insurer requests | Export a full history for one work package |
| Deployment control | Data residency and site network limits | On-premise or private deployment option |
If a shortlist cannot pass the offline test and the permit test in a real trial, the rest of the comparison is academic. Those two are where mining deployments fail in the first quarter.
Join Doitify Today
Move projects forward without the chaos: all your tasks, progress, and team reports in one unified workspace. Built for companies, startups, and remote teams — with a quick setup and a free trial.
Which tools fit which mining job?
No single product covers a mine end to end, which is why the honest answer is a two-layer architecture.
| Tool | Layer | Strength | Limitation |
|---|---|---|---|
| Oracle Primavera P6 | Capital project scheduling | The de facto standard for large capital projects and EPCM contracting; resource-loaded schedules, critical path, earned value | Heavy to learn and administer; licence and implementation cost is substantial |
| SAP PM or IBM Maximo | Asset and maintenance | Work orders, asset hierarchy, spare parts, compliance history for mobile fleet and fixed plant | Not a project planning tool; poor fit for capital project scheduling |
| Hexagon or RPMGlobal | Mining-specific planning | Short-term scheduling, fleet allocation, and maintenance planning aligned to mining processes | Specialised; integrates rather than replaces a PM layer |
| Planview | Portfolio and capital allocation | Portfolio prioritisation across a multi-asset group, resource capacity | Enterprise implementation timeline and cost |
| Doitify | Execution and coordination | Tasks, subtasks, dependencies, Gantt, workload, reports, documents, automations in one workspace | Best as the execution layer beneath a P6 schedule, not a replacement for it |
| Redmine or OpenProject | Self-hosted execution | On-premise control, low licence cost, adaptable workflows | Requires internal operations capacity; limited mining-specific function |
The common failure is buying the first row and expecting it to run daily execution, or buying the last row and expecting it to schedule a 900-million-dollar concentrator expansion. Two layers, one integration, and a clear rule about which system is the source of truth for dates is the pattern that holds.
What does this software actually cost at mine scale?
Licence costs in mining are rarely the deciding number, but they are the one procurement will ask about first, so it is worth being precise.
Consider a mid-tier operator with 250 people who need access: 40 in project controls and engineering, 90 in maintenance and operations supervision, and 120 contractors and coordinators. A capital scheduling layer for the 40 project-controls users, at typical enterprise P6 licensing plus one scheduling add-on, is commonly quoted in the low hundreds of thousands per year once support and implementation are included. A self-hosted execution layer for all 250, at an enterprise per-user rate, is a different order of magnitude.
Take a concrete execution-layer calculation: 250 users at 12 dollars per user per month is 36,000 dollars a year, or 250 at 35 dollars is 105,000 dollars. Implementation, integration with the CMMS, and data migration typically add 0.5 to 1.5 times the annual licence in the first year. So the realistic first-year range for a 250-user execution layer is 55,000 to 260,000 dollars, and that range is wide because implementation, not licence, is the variable.
Now put that next to the number that matters. If the same system removes one day of delay from a single major shutdown, the licence is paid for. That is the argument to make, and it needs to be made with the operator’s own throughput figures rather than an analyst’s average.
How do you value a single day of delay?
Build the number from the site’s own data, because it varies by an order of magnitude between operations.
A 20 million tonne per year concentrator produces about 54,800 tonnes per day at steady state (20,000,000 / 365). At a margin of 30 dollars per tonne, a full day of lost throughput is about 1.64 million dollars. A 12-day mill shutdown that runs one day long therefore costs roughly 1.6 million dollars in deferred margin, before contractor standby.
The standby line is smaller but visible: 60 contractors on site at an average of 1,100 dollars per day each is 66,000 dollars for the extra day, and the mobile equipment and crane hire add more. Call it 1.7 million dollars for a one-day overrun.
Compare that to the software decision. The difference between a 36,000 dollar and a 105,000 dollar execution layer is 69,000 dollars a year. One avoided day of shutdown overrun is 25 times that gap. This does not mean buying the most expensive tool; it means the licence comparison should never be the reason a shutdown plan lives in spreadsheets.
Two cautions. Lost throughput is not always lost revenue, because stockpiles and market timing can absorb some of it, so use the operator’s marginal margin rather than headline price. And the counterfactual matters: software reduces delay only when the constraint is coordination, not when it is a shovel that broke.
How should permits and contractor onboarding live in the system?
They should live in the system that assigns work, with hard gates rather than reminders. This is the area where generic tools quietly create legal exposure.
A permit-to-work process has four properties a project tool must respect. It needs an approval chain with named roles, not a free-text field. It must record time, because a permit is valid for a shift, not indefinitely. It must be immutable after approval, with corrections recorded as amendments. And it must be queryable by location and activity, because the first question after an incident is which permits were live in that area.
Contractor onboarding has similar mechanics. A contractor who has not completed site induction, medical clearance, and equipment competency should not be assignable to a task that requires them. That is a data relationship, not a policy document: the assignment control reads from the competency record.
The arithmetic is unglamorous but persuasive. Take 1,800 permits a year, with a rework rate of 6 percent because of missing isolations or wrong area codes: 108 reworked permits at 2.5 hours each is 270 hours, roughly 30,000 dollars of supervisor time, plus a shutdown delay risk that is far larger. Gating the form on area and isolation type removes most of that rework, and the audit trail it produces is the same artefact the regulator asks for.
What about connectivity and roster realities?
Design for the site, not for the head office. Three practical patterns make the difference between adoption and abandonment.
Offline-first capture. Supervisors in a pit do not stand still waiting for a page to load. The tool must accept a task update, a photo, and a note with no signal, queue them, and reconcile on reconnect without silently overwriting someone else’s edit. Test this by putting a phone in flight mode for four hours and using it normally.
Shift handover as a first-class artefact. Mining runs on handover. A structured handover note attached to the crew, the area, and the outstanding work items is worth more than any dashboard, because it is read at the moment decisions are made. If your tool cannot produce a handover sheet in one action, supervisors will keep using paper and the system becomes a reporting tax.
Roster-aware assignment. A 2:1 fly-in fly-out roster means half the assignees are off site at any time. Workload views that ignore roster calendars show false overallocation and get ignored. The requirement is simple: the system must know who is on site this week.
Low-bandwidth defaults. A Gantt chart with 4,000 activities will not load over a degraded satellite link. Provide filtered views by area and package, and cache the last view so a supervisor can open it underground.
What compliance questions will auditors ask?
Auditors and regulators do not ask whether you have software. They ask for evidence, and the evidence has to come out of the system quickly.
Expect requests for: the approval history of a specific permit, the induction and competency records of everyone who worked in an area during a period, the change history of a safe work procedure, the maintenance status of equipment involved in an incident, and the records retention policy that governs all of it.
Several frameworks shape those requests. ISO 45001 covers occupational health and safety management and requires documented evidence of hazard identification and incident response. ISO 55000 frames asset management, which is why CMMS records matter to a project system. ISO 14001 covers environmental management, and tailings and water obligations increasingly sit inside it. In the United States, mine operators report certain incidents to MSHA under 30 CFR Part 50, with immediate notification required for the most serious events, and the reporting chain begins on site. In Australia, state regulators such as Resources Safety and Health Queensland impose their own notification and record-keeping duties, and ICMM’s critical control approach shapes how major operators structure their evidence.
Practically, this means three software requirements: retention that outlives staff turnover, export in a readable format without vendor help, and access logs that show who saw and changed what. On-premise or private deployment remains common in mining for exactly this reason, and the trade-off is that patching and backup become your obligation, which is a real cost covered in our on-premise comparison.
What are the trade-offs of the two-layer architecture?
The two-layer pattern works, but it is not free, and the costs are predictable.
Duplication risk. Dates exist in the schedule and in the execution tool. The rule must be explicit: the scheduler owns the baseline and the milestone dates; the execution tool owns the task-level plan and the daily status. Any other arrangement produces two truths and a weekly argument.
Integration cost. A CMMS integration is a project, not a connector. Budget 6 to 12 weeks for a two-way sync that handles equipment hierarchy, work order status, and failure codes, and expect the first version to be read-only.
Training load. Project controls staff need P6 fluency; supervisors need a ten-minute mobile workflow. Treating those as one training programme wastes both audiences.
Vendor concentration. Heavy dependence on one scheduling vendor creates renewal risk, which is why export capability in an open format belongs in the contract.
Speed versus control. A lightweight tool rolls out in weeks and gets used; a heavyweight one takes a year and gets resented. The compromise that works is a light execution layer beneath a rigorous schedule, with the schedule feeding milestones rather than every task.
How do you run a 90-day selection?
Three phases, each with a decision at the end.
Days 1 to 30: define the constraint. Interview project controls, maintenance planning, and two site supervisors. Write the single sentence that describes what is failing, such as “shutdown progress is reported 36 hours late and the permit register is a spreadsheet”. That sentence filters the market faster than a 300-line requirements document.
Days 31 to 60: test in the field. Two vendors, one real package, offline phones, real permits, real contractor records. Score against the nine requirements table, and weight offline capture and permit integrity heavily. A demo room cannot show you either.
Days 61 to 90: price the third year. Include licences, implementation, integration, training, and the internal FTE who will administer it. Ask what happens at renewal, and ask for the export format in writing.
If a vendor cannot support a field trial, that is the answer, and it is cheaper to learn it in week 40 than in month 14.
Where does Doitify fit in a mining operation?
Doitify is our product, so treat this as disclosure rather than an independent review. It is built as one workspace for projects, tasks, sub-tasks, checklists, owners, and due dates, with Kanban boards, Gantt charts, roadmaps, calendars, workload views, work and performance reports, automations, import and export, and project documents. Doitify Copilot and AI Coach help convert a stated goal into tasks and a plan.
In mining terms, that makes it the execution and coordination layer: shutdown task lists, contractor mobilisation checklists, permit and handover records modelled as structured tasks with owners and evidence, and reports that show progress by area without someone rebuilding a spreadsheet at 5 a.m. It reads and exports in standard formats so a P6 milestone feed remains the schedule of record. Where the requirement is a fully air-gapped deployment with your own database administrators, confirm the current hosting options with our team before planning a migration, because that requirement deserves a tested answer rather than a promise.
FAQ
Conclusion
The best project management software for mining companies is not one product but a disciplined pair: a scheduling system that owns the baseline and a work management layer that owns daily execution on site. Primavera P6, Planview, SAP PM or Maximo, and Hexagon each do a job that the others cannot, and the integration between them is the deliverable that actually determines success.
Choose the execution layer by testing it offline, by testing a real permit, and by asking what the third year costs. Then value one day of delay with your own numbers and hold that figure next to the licence. On a mine, the software is never the expensive part; the delay is.